The plant expansion at Willamette’s Surepine facility required the design of 21 pneumatic systems including low pressure conveying systems, high pressure conveying systems and dust collection systems.  Eagle/WPS personnel led the design and implementation of the project.  The design work was broken into two phases:

Preliminary Engineering

The scope of work included the development of preliminary layouts and budget estimates for the pneumatic systems associated with the addition of a new forming line and press.  General arrangement drawings, scope of work, and equipment specifications were generated for the bid packages.

Final Engineering

Once the project was approved, the final engineering on the pneumatic systems was performed. Final engineering included the design of all support structures and foundations for the pneumatic systems.

WPS provided complete fabrication and installation services for these systems.